The Chesterfield Energy Reliability Center would feature four of GE’s 7FA.05 simple-cycle gas turbines, each with an output ...
Listen to this article Dominion Energy submitted an application with the Virginia State Corporation Commission Monday to install four natural gas-fired turbines on 95 acres at the utility’s ...
Dominion seeks SCC approval for proposed Chesterfield gas plantCHARLOTTESVILLE, Va. -- Dominion Energy recently filed with ...
To meet the projected demand, Dominion has adopted an “all of the above” approach to power generation, which has led to it expanding the capacity of several of its existing natural gas plants. In ...
Hosted on MSN10mon
Chesterfield residents voice concerns about proposed power plantUnder the plan by Dominion Energy, the Chesterfield Energy Reliability Center is slated to be built within the James River Industrial Center and use four turbines to generate 1,000 megawatts of ...
Dubbed the Chesterfield Energy Reliability Center (CERC), the facility, which is expected to cost $1.47 billion, will generate 944 megawatts of energy. The plant will provide electricity to ...
Dominion Energy has asked Virginia officials to approve its request to build a new 1-GW natural gas-fired power plant, as the company seeks to add more generation capacity to ...
This community group has been pushing back against this proposal for months, arguing — among several other concerns — that this proposed Chesterfield Energy Reliability Center (CERC ...
The "Chesterfield Energy Reliability Center" would consist of four natural gas-powered turbines that could produce enough energy to power up to 250,000 homes. It would serve as back-up generation ...
Dominion Energy has asked Virginia officials to approve its request to build a new 1-GW natural gas-fired power plant, as the company seeks to add more generation capacity to help serve surging demand ...
Some results have been hidden because they may be inaccessible to you
Show inaccessible results